Lake Clifton Park High SchoolBaltimore City Public Schools / Maryland Stadium Authority

From cost estimating during the feasibility study to the civil engineering of the site to the proactive advocacy for the development of a IART credit bank with MDE, this project is an example of MK’s commitment to our clients.

Statistics

Construction Cost
$49 Million
Year Completed
2019
Square Feet
183,000
Acres
4

Team Members Involved

member involved img
Marianne K. Crampton, PE
member involved img
Paul D. Crampton
member involved img
Steve McCalmont
member involved img
George Bakalyar
member involved img
Seth Glasser​
member involved img
Amanda Pizza, PE

Partners

Architect | Hord Coplan Macht

700 E Pratt Street #1200
Baltimore, MD 21202
(410) 837-7311

Project Overview

This historic high school building (previously named the Fairmount-Harford Building) was originally built in 1923 in the Clifton Park neighborhood of Baltimore City. To renovate and expand the building, the Maryland Stadium Authority issued its first design/build procurement. Southway Builders & MCN Build partnered with architect Hord Coplan Macht to complete the design and construction for the renovation/addition project on an accelerated schedule.

Credit: Hord Coplan MachtCredit: Hord Coplan Macht

Our Approach

We provided the cost estimating for four alternatives during the study phase. Once awarded as a design/build, we began to research and design the site. To accommodate the building and adjacent activities, MK prepared an additional subdivision to the lot for expansion. New sidewalks improve pedestrian access and safety. Infrastructure improvements included new parking, drop-off, and emergency access areas. Additional stormwater management practices were implemented to accommodate the additional impervious area of the gymnasium addition and bring the site up to current standards.

The Results

Because of an opportunity to overmanage the impervious area of the Fairmount-Harford Building site, we proposed the creation of an MDE credit bank for treated impervious area on behalf of the Maryland Stadium Authority. This provides flexibility for future City Schools projects, as these consistently tight sites often struggle to achieve the requirements of stormwater management regulations.

Mother Seton Academy Mother Seton Academy Gymnasium

By thoughtfully designing and programming a tiny lot, the Mother Seton Academy gained a learning garden, pocket park, and outdoor classroom for their middle school students.

SEE CASE STUDY

Arundel Community Development Services (ACDS) Severn Center

The Severn Center is a project 20 years in the making, a multi-purpose center created for children, youth, families, seniors – a place of community involvement and impact.

Image Credit: Murphy & Dittenhafer

SEE CASE STUDY

Baltimore City Urban Development

MK is practiced in the legislative and development procedures, policies, and personnel associated with the Baltimore City review and approval process.

SEE CASE STUDY

Baltimore County Public Schools Berkshire Elementary School

The site design for this prototype school incorporated challenging typography, innovative stormwater management, upgraded utilities, safe access, and phasing to create a beautiful new school for the community.

SEE CASE STUDY